| Date of Contract |
Our Client |
Description of work |
Main Equipment |
 |
| 2009 |
Westingcorp |
Platinum Australia 132kV protection and control schemes |
|
| 2008 |
ESKOM |
Cable feeder modular protection and control schemes |
Reyrolle Argus, Solkor R/Rf |
| 2008 |
Megatron Federal |
120kV protection and control schemes |
Reyrolle Ohmega, Duobias M, Argus, MicroTAPP, RMS 2HSM5, 1A54 |
| 2007 |
Mega HVT |
Tata Steel furnace transformer protection schemes |
Siemens 7SJ60, RMS 2HSM5 |
| 2007 |
Megatron Federal |
120kV protection and control schemes |
Reyrolle Ohmega, Duobias M, Argus, MicroTAPP, RMS 2HSM5, 1A54 |
| 2007 |
Msunduzi Electricity |
132kV substation integration |
Cybectec SMP16 |
| 2007 |
Megatron Federal |
120kV protection and control schemes |
Reyrolle Ohmega, Duobias M, Argus, MicroTAPP, RMS 2HSM5, 1A54 |
| 2007 |
De Beers |
33kV protection and control schemes |
Reyrolle Argus, RMS 2V164, 2HSM5 |
| 2006 |
Swaziland Electricity Commission |
66kV transformer protection schemes |
Reyrolle Ohmega, Duobias M, Argus, MicroTAPP, RMS 2HSM5, 1A54 |
| 2006 |
Toyota |
132kV protection and control schemes |
Reyrolle Duobias M, Argus, MicroTAPP, RMS 2HSM5 |
| 2006 |
Merz & McLellan |
Msunduzi Electricty 132kV substation integration |
Cybectec SMP16 |
| 2006 |
Swaziland Electricity Commission |
66kV transformer protection schemes |
Reyrolle Duobias M, Argus, MicroTAPP, RMS 2HSM5, 1A54 |
| 2005 |
MARQOTT Power Projects |
Richards Bay Electricty 132kV protection and control schemes |
Reyrolle Duobias M, Argus, MicroTAPP, RMS 2HSM5 |
| 2005 |
CONCO |
Msunduzi Electricty 132kV substation integration |
Cybectec SMP4 |
| 2005 |
LEBA Consulting |
De Beers 11kV substation integration |
Cybectec SMP16 |
 |
 |
 |
 |
 |